Short answer: If your building has three or more apartments and wood-supported balconies, decks, stairways or walkways more than six feet above the ground, California's SB 721 (Health and Safety Code Section 17973) required a licensed inspection by January 1, 2026, and every six years after that. When you sell, the law says copies of the inspection reports must be disclosed and delivered to the buyer. If you skipped the inspection or still have open repairs, buyers will find out in escrow, so it pays to deal with it before you list.
Updated: November 2026. We'll refresh this post if the law or the City's guidance changes.
Here's what the law requires, how it plays out in a sale, and a hypothetical repair timeline.
What is the SB 721 balcony inspection law?
SB 721 is a 2018 state law that added Section 17973 to the California Health and Safety Code. It requires owners of buildings with three or more multifamily dwelling units to have the building's "exterior elevated elements" inspected. The goal, in the law's words, is to confirm those elements and their waterproofing are "in a generally safe condition, adequate working order, and free from any hazardous condition caused by fungus, deterioration, decay, or improper alteration."
An exterior elevated element is a balcony, deck, porch, stairway, walkway or entry structure, with its supports and railings, that extends beyond the building's exterior walls, has a walking surface more than six feet above the ground and relies in whole or in substantial part on wood for its structure. Many older LA apartment buildings have exactly that: wood balconies, exterior stairs and walkways.
Which LA apartment buildings does SB 721 cover?
It covers buildings with three or more multifamily dwelling units that have wood-supported elevated elements, so it can apply to a triplex or fourplex as well as a 40-unit building. It doesn't apply to single-family homes or duplexes, and it doesn't apply to condominiums and other common interest developments, which fall under a separate law (SB 326, Civil Code Section 5551).
Because it's a state law, it applies across Los Angeles County, including the San Fernando Valley, the Westside, Beverly Hills and the South Bay cities. Cities may add stricter rules of their own, so check with the city where your building sits. In the City of Los Angeles, the Los Angeles Housing Department (LAHD) publishes the E3 guidance for apartment buildings and takes E3 complaints at (866) 557-7368.
When was the inspection due?
The first inspection was originally due January 1, 2025. AB 2579 (2024) moved the deadline to January 1, 2026, and the current statute requires an inspection by that date and by January 1 every six years after it, which makes the next round due January 1, 2032.
Two exceptions matter. A building whose permit application was submitted on or after January 1, 2019 must be inspected no later than six years after its certificate of occupancy. And if asbestos is found during the inspection, the owner gets up to nine months to abate it and then three months to finish the inspection. If your building had no inspection by January 1, 2026 and neither exception applies, it is out of compliance today.
Who can do the inspection and what is in the report?
The owner hires the inspector, who must be a licensed architect, a licensed civil or structural engineer, a contractor with an A, B or C-5 license and at least five years of experience building multistory wood-frame buildings, or a certified building inspector or building official. The inspector can't be employed by the city while doing the work.
The inspector must look at a sample of at least 15% of each type of elevated element, assess the load-bearing parts and the waterproofing, and give the owner a stamped or signed written report within 45 days. The report covers current condition, expected future performance and service life, and any further inspection needed, with photos. If an element is an immediate threat to safety, the inspector must send the report to the local enforcement agency within 15 days, and the owner must block access or make emergency repairs right away.
How long do I have to make repairs?
For repairs that aren't an emergency, the owner must apply for a permit within 120 days of receiving the report, then finish the work within 120 days after the permit is approved unless the local agency grants more time. Repairs must be done by a licensed contractor, following the inspector's recommendations and the building code.
If repairs aren't done within 180 days, the inspector must notify the local enforcement agency and the owner. If they still aren't done 30 days after that notice, the owner can be charged a civil penalty of $100 to $500 per day, and the city can record a building safety lien against the property.
| Step (hypothetical dates) | Rule in Section 17973 | Date |
|---|---|---|
| Inspector finishes the site visit | Written report due within 45 days (by Mar 18, 2027) | Feb 1, 2027 |
| Owner receives the report | Permit application due within 120 days (by Jul 13, 2027) | Mar 15, 2027 |
| Owner applies for the repair permit | Within the 120-day window | Apr 15, 2027 |
| Permit approved | Repairs due within 120 days of approval | Jul 1, 2027 |
| Repair deadline | Unless the local agency grants more time | Oct 29, 2027 |
Hypothetical example only. It shows how the statutory clocks run; it is not a real property, and your local agency can grant extensions.
What does SB 721 require when I sell?
Section 17973 says copies of all inspection reports must be kept in the owner's permanent records for at least two inspection cycles and "shall be disclosed and delivered to the buyer at the time of any subsequent sale of the building." So the report is part of your due diligence package, along with the rent roll, leases and RSO paperwork.
The law also makes the owner of the building responsible for compliance and for ongoing maintenance. When the building changes hands, open repair items, permits in progress and any penalties become the new owner's problem, and buyers know it. Expect a buyer's inspector to read the report closely and to ask for the final report confirming repairs were finished, which the inspector provides if the owner requests it.
Should I inspect and repair before I list?
Usually it helps to at least have the inspection done. A report in hand lets you price the building with the facts known, rather than leaving the buyer to guess at a worst case during escrow. From there you have three common choices: finish the repairs and deliver the final report, get contractor bids and offer a price reduction or credit, or sell as-is with the report disclosed and the price set accordingly.
Timing matters. Permits and repairs follow the 120-day clocks above, which can be longer than a typical escrow. If you are lining up a 1031 exchange or a closing date, start early. Pair the inspection with other pre-sale items buyers check, like soft-story retrofit status and deferred maintenance. See our soft-story retrofit guide and our post on what to fix before selling.
Do small buildings like triplexes and fourplexes need it?
Yes, if they have qualifying wood elevated elements. The law starts at three multifamily dwelling units, so a triplex or fourplex with wood stairs or a balcony more than six feet up is covered, while a duplex is not. A clean report answers a question buyers and their inspectors will ask anyway. See how to sell a triplex and, in the South Bay, our South Bay apartment seller guide.
Selling an LA apartment building?
Call David Saghian at (310) 401-1559 or request a free property valuation. We can help you decide what to fix, what to disclose and how it affects your net proceeds. We don't do inspections or give legal advice; bring the report to your inspector, contractor and attorney. DRE 01992252.
This article is general information, not legal or engineering advice. Rules can change and depend on your building, so confirm requirements with a licensed inspector, your city and a real estate attorney before you list or sign anything. The repair timeline is hypothetical and doesn't describe a real property or client.